Jul. 03, 2026
Parameter Item | Specification Value |
Operating Weight | 1,720 kg |
Standard Bucket Capacity | 0.05 m³ |
Machine Width | Retractable undercarriage, adjustable from 990–1,240 mm |
Swing Structure | Zero-tail swing design; tail remains within track width, enabling close operation against walls and fences |
Boom Configuration | Side-offset swing boom with left-right offset function, suitable for narrow trench and wall-side operation |
Engine | Kubota D902, rated power 11.8 kW |

Soil Condition | Daily Output | Hourly Output |
Loose soil (residential backfill, farmland soil, loose fill) | 280–400 m³/day | 30–50 m³/h |
General soil (mixed with minor bricks and rubble) | 200–280 m³/day | Approx. 30 m³/h (estimated) |
Hard compacted soil (old foundation sites, hardened soil layers) | 150–200 m³/day | Approx. 20 m³/h (estimated) |
Statistical Index | Construction Output Standard |
Daily Trenching Length | 90–140 m/day |
Hourly Trenching Length | 12–18 m/h |
Material Type | Daily Output | Hourly Output |
Ordinary concrete slab (10–20 cm thick) | 40–60 ㎡/day | 4–7 ㎡/h |
Aged pavement & reinforced concrete structure | 30–45 ㎡/day | 4–6 ㎡/h (estimated) |
Construction Process | Daily Output | Remarks |
Soil Backfilling & Site Leveling | 300–450 m³/day | Loose soil with low digging resistance for faster operation |

Construction Type | Calculation Formula | Practical Calculation Example |
Earthwork Volume | Daily Output = Hourly Output (m³) × Effective Working Hours | Loose soil: 40m³/h × 6h = 240m³/day |
Trenching Length | Daily Trench Length = Hourly Trenching Meterage × Effective Working Hours | Standard trench: 15m/h × 7h = 105m/day |
Breaking Area | Daily Breaking Area = Hourly Breaking Area (㎡) × Effective Working Hours | Concrete breaking: 5㎡/h × 6h = 30㎡/day |
Note on Effective Working Hours: Refers to actual productive working time after deducting equipment setup, staff breaks, material transportation and site access delays. A standard 8-hour shift generally provides 6–7 hours of effective working time under normal conditions.

Influencing Factor | Productivity Variation | On-site Planning Suggestions |
Site Accessibility & Space | Confined spaces such as basements, narrow alleys and greenhouses reduce productivity by 20%–35% compared with open sites | Reserve 25%–30% construction time allowance for projects in narrow working spaces |
Soil & Material Hardness | Hard and compacted soil reduces productivity by 10%–20% compared with loose soil | Conduct pre-construction site soil survey to revise quantity estimation data |
Simultaneous Excavation & Loading | Combined excavation and truck loading reduces overall productivity by 25%–40% | Separate excavation and transportation procedures if the construction schedule permits |
Operator Proficiency | Experienced operators achieve 25%–35% higher efficiency than novice operators | Take operator skill level into account when formulating construction schedules |

Category | Detailed Description |
Applicable Scenarios | Narrow alley operation, basement and indoor renovation & demolition; municipal pipeline and farm ditch trenching; courtyard civil works; small-scale floor demolition projects |
Inapplicable Scenarios | Large-scale earthmoving and outward transportation, hard rock breaking, deep foundation excavation exceeding 3 meters |
Latest FAQ
Yuchai Compact Excavators Worldwide